Delfin LNG asks FERC for a sixth extension, to 2030, for its onshore facilities, Docket No. CP15-490-005

Delfin's October 30 request would move the in-service deadline for its Cameron Parish metering, compression and pipeline facilities to September 28, 2030, thirteen years after FERC certificated them. Interventions and comments are due November 25.

Entered by
Public Record Service
Date
Sources
8 cited

Summary

Delfin LNG LLC asked the Federal Energy Regulatory Commission on October 30, 2026, for three more years to build the onshore metering, compression and piping facilities in Cameron Parish, Louisiana, that would feed its floating LNG export port, moving the in-service deadline from September 28, 2027, to September 28, 2030 [1, 2]. FERC’s notice of the request, Docket No. CP15-490-005, is dated November 10 and appears in the November 16 Federal Register at 91 FR 73576, with interventions and comments due November 25 [1]. The facilities were certificated under section 7(c) of the Natural Gas Act in 2017 with a two-year construction window; this is the sixth request to extend it [1, 2].

What the record shows

What the facilities are

FERC’s jurisdiction here is narrow. The certificate covers “just over 2-miles of pipeline, new compression and appurtenant facilities within the fenceline of an existing gas facility, and a new metering and regulation station,” in the words of Delfin’s filing, used only to deliver gas to a deepwater port about 37.4 to 40.8 nautical miles offshore [2]. The port itself, including its moored floating liquefaction vessels, is licensed by the Maritime Administration and the Coast Guard under the Deepwater Port Act of 1974 [1, 3].

What Delfin says changed since 2023

The 2023 extension rested on contracts and a pending investment decision that had not yet arrived [3]. Delfin’s new filing lists what has happened since [2]:

Date Event, as stated in Delfin’s filing
March 10, 2025 DOE extends the non-FTA export commencement deadline to June 1, 2029
March 21, 2025 Maritime Administration announces issuance of the final deepwater port license
June 15, 2025 Delfin submits the executed license, making it fully effective
November 25, 2025 DOE amends the project to three floating vessels and extends the export deadline to June 1, 2031
June 3, 2026 Final investment decision, about $5 billion, on the first floating LNG vessel
July 7, 2026 Fifth Circuit denies petitions for review of the license, Case No. 25-60282

DOE’s own March 2025 announcement confirms the first step and states the authorization covers up to 1.8 Bcf/d of exports to non-free trade agreement countries [6]. The license step followed Executive Order 14154, whose section 8(b) through (d) directed the Maritime Administration to decide within 30 days whether post-decision changes to a deepwater LNG port presented “seriously different” environmental consequences; Delfin’s filing says it was the only project the provision covered [2].

The filing puts the investment decision at roughly $1.41 billion in equity and about $3.55 billion in project-financed debt, with a group led by Global Infrastructure Partners, part of BlackRock, and including Mitsui O.S.K. Lines, Vitol and Diameter Capital Partners [2]. Oil & Gas Journal reported the same investor group, a 4.4 million tonne-per-year capacity for the first vessel, production starting in 2030, and long-term sales agreements with Vitol, Expand Energy, Centrica and Gunvor [7]. LNG Prime reported Delfin’s description of the unit as the first floating liquefaction facility in the United States [8].

Why 2030

Samsung Heavy Industries is building the first vessel in South Korea under an engineering, procurement, construction and integration contract, with Black & Veatch on topside liquefaction [2]. Delfin expects the vessel at the port in the first half of 2030 and projects feed gas will need to flow through the onshore facilities “by approximately July 1, 2030” [2]. It plans to finish those facilities by mid-2030 and asks for September 28, 2030, “to provide a small additional buffer” and to avoid needing another extension [2].

Where it sits in the process

What standard will FERC apply to the Delfin request?

Under 18 CFR 157.20(b), every certificate carries a deadline, set in the order, by which construction must be completed and made available for service [5]. FERC extends such deadlines for “good cause,” which it has said a sponsor can show by demonstrating “good faith efforts to meet its deadline” that were frustrated by circumstances [3]. The notice limits what parties may argue. FERC “will not consider arguments that re-litigate the issuance of the certificate order,” including whether the project was in the public convenience and necessity and whether the environmental analysis complied with NEPA [1].

Who decides, and how fast?

That depends on whether anyone contests the request. If no one does, the Director of the Office of Energy Projects or a designee acts on it [1]. If an intervenor disputes a material issue, the Commission itself acts, and it “will aim to issue an order acting on the request within 45 days” [1]. The comment window is 15 calendar days, ending 5:00 p.m. Eastern Time on November 25, and no reply comments or answers will be considered [1].

How the deadline has moved

Extension Granted by New in-service deadline
Original certificate (Sept. 28, 2017) Commission Sept. 28, 2019
First through fourth (2019 to 2022) Two delegated letter orders, then two Commission orders, one year each Sept. 28, 2023
Fifth (Oct. 4, 2023) Commission, 185 FERC ¶ 61,009 Sept. 28, 2027
Sixth (requested Oct. 30, 2026) Pending Sept. 28, 2030 requested

Sources for the table: the 2023 order and the November notice [3, 1]. If granted, the deadline would fall thirteen years after the certificate issued, by this report’s count from those dates.

What the record does not show

  • Who will file. As of the notice, the -005 sub-docket held only Delfin’s request and FERC’s notice [1, 2]. Whether Sierra Club, Public Citizen or Centrica, all intervenors in 2023, file again is not known [3].
  • Vessels two and three. Delfin says their timing depends on separate investment decisions, and that it has one sales agreement, with Centrica, for the second vessel and is negotiating with MidOcean Energy over up to 50% of it [2]. The extension request is sized to the first vessel only.
  • Total capacity. Oil & Gas Journal’s article gives up to four vessels and 13.3 million tonnes per year in its text and up to three vessels and 13.2 million in a caption [7]. Delfin’s filing describes the final design as three vessels “with the same total liquefaction and export capacity” as the earlier four [2]. The 2023 order described four vessels of about 3.0 million tonnes per year each [3].
  • Endangered species. In 2023, FERC said the listing of the Rice’s whale alone did not trigger further consultation, and that the Maritime Administration and Coast Guard could coordinate any consultation with NMFS on critical habitat [3]. Delfin now says the Maritime Administration consulted NMFS during final licensing [2]. That consultation’s outcome is not in the FERC record cited here.
  • The DOE orders and the Fifth Circuit decision. Their content appears in this record only as Delfin describes and quotes it [2].

Positions on the record

Delfin. The company argues its case is “stronger” than in 2023: the onshore facilities’ only customer, the port, cannot take gas until 2030, the project has reached a positive investment decision, and denial “would undermine the jurisdiction of other agencies” [2]. It cites FERC extensions for other export projects, noting that “[m]ost of those projects, unlike Delfin, have not achieved a positive FID,” and says an extension is an administrative action that needs no new NEPA review [2]. The filing is signed by J. Patrick Nevins of Latham & Watkins [2].

Sierra Club, in 2023. Sierra Club’s 2023 protest called that request Delfin’s fifth and said a grant would mean “up to a decade since initial licensing to bring the project online” [4]. It argued Delfin had not built because “it chose not to or because there was insufficient demand,” and that “[a] mere market downturn is not a sufficient justification for an extension under FERC’s precedents” [4]. It also pointed to the Rice’s whale, with “a remaining population of less than 50 individuals,” and to proposed critical habitat lying beyond the port, which vessel traffic would cross [4].

The Commission, in 2023. FERC rejected those arguments. It found that “where, as here, the sole purpose of the project is to serve the needs of a single customer,” that customer’s difficulties can justify an extension, and that Delfin, unlike the sponsor in Chestnut Ridge, had not let its authorization “lie dormant” [3]. Commissioner James Danly concurred separately, writing that “[e]xtension of time proceedings are not an invitation to re-open the underlying dockets” [3]. Centrica LNG Company filed in support in 2023 [3].

Delfin asked FERC, “or Staff acting by delegated authority,” to grant the request “promptly” [2]. Which of the two acts depends on what is filed by November 25.

Reading-room questions

Questions readers bring to this record, answered from the documents cited below.

What deadline is Delfin LNG asking FERC to extend?
The date by which its FERC-certificated onshore facilities in Cameron Parish, Louisiana must be built and placed in service, now September 28, 2027 [1]. Delfin asks for September 28, 2030 [2].
How many times has FERC extended Delfin's onshore deadline?
Five times: four one-year extensions from 2019 through 2022, then a four-year extension in October 2023 [1, 3]. The October 30, 2026 request would be the sixth [1].
When are comments on the Delfin LNG extension request due?
Interventions and comments are due by 5:00 p.m. Eastern Time on November 25, 2026, and FERC will not consider reply comments or answers [1].
Can opponents reargue the Delfin certificate or its environmental review in this proceeding?
No. The notice says FERC will address only whether Delfin has shown good cause, not arguments that re-litigate the certificate or its NEPA analysis [1]. FERC applied the same limit in 2023, when it declined to revisit Sierra Club's earlier arguments [3].
Does FERC regulate Delfin's floating LNG vessels?
No. The deepwater port and its floating vessels fall under the Maritime Administration and the Coast Guard under the Deepwater Port Act; FERC's certificate covers only the onshore metering, compression and pipe [1, 3].

Note on sourcing

The account of the 2025 Maritime Administration license, the two 2025 DOE extension orders, the November 25, 2025 DOE amendment to three floating vessels, the Fifth Circuit's July 7, 2026 denial of review in Case No. 25-60282, and the financing split behind the June 3 investment decision comes from Delfin's October 30 filing; this report does not draw on those orders, the court decision or Delfin's own release directly, except DOE's March 10, 2025 announcement. As of the November 10 notice, the CP15-490-005 sub-docket held only Delfin's request and the notice; whether anyone intervenes or protests by November 25 is not yet known. Sierra Club's positions are those it filed in the 2023 extension proceeding, not in the current one. Totals of years and extensions are this report's count from the dates in the record.

Sources

  1. Delfin LNG LLC; Notice of Request for Extension of Time, Docket No. CP15-490-005 (91 FR 73576, FR Doc. 2026-23232)Federal Energy Regulatory Commission, November 16, 2026 · govinfo.gov
  2. Delfin LNG LLC, Request for Additional Three-Year Extension of Time, Docket Nos. CP15-490-000 and -004 (eLibrary Accession No. 20261030-5440)Delfin LNG LLC, October 30, 2026 · elibrary.ferc.gov
  3. Delfin LNG LLC, Order Granting Extension of Time, 185 FERC ¶ 61,009 (Docket No. CP15-490-004)Federal Energy Regulatory Commission, October 4, 2023 · elibrary.ferc.gov
  4. Protest in Opposition to Delfin LNG's Request for Extension of Time, Docket Nos. CP15-490-000 and -004 (eLibrary Accession No. 20230809-5163)Sierra Club, August 9, 2023 · elibrary.ferc.gov
  5. 18 CFR 157.20, General conditions applicable to certificatesFederal Energy Regulatory Commission, accessed 2026-11-15 · ecfr.gov
  6. DOE Issues Extension to Delfin LNG ProjectU.S. Department of Energy, March 10, 2025 · energy.gov
  7. Delfin Midstream takes $5-billion FID for first FLNG vesselOil & Gas Journal, June 4, 2026 · ogj.com
  8. Delfin takes FID on first FLNGLNG Prime, June 3, 2026 · lngprime.com

Subject headings

Cross-references

Other register entries filed under the same subject headings.

  1. No. 0030 · Report · 3 shared headingsFERC opens scoping on Longboard LNG import terminal off Oʻahu, Docket No. PF26-10-000
  2. No. 0026 · Record of decision · 3 shared headingsFERC staff issues final EIS for Sabine Pass Stage 5 LNG expansion, Docket No. CP24-75-001
  3. No. 0015 · Report · 3 shared headingsFERC opens scoping on Venture Global's CP2 LNG Expansion Project, Docket Nos. CP26-530 and CP26-533