NRC notices Part 2 of Holtec's Pioneer SMR-300 construction permit application, Docket Nos. 50-616 and 50-617

The NRC's November 10 notice (91 FR 72577) starts four weeks of receipt notices for the preliminary safety analysis report Holtec filed September 30 for two SMR-300 units at Palisades. Staff have not yet decided whether to docket it, and the dates set in February for the limited work authorization still run into 2027.

Entered by
Public Record Service
Date
Sources
11 cited

Summary

Holtec already holds an NRC exemption to build permanent excavation walls at the Pioneer site in Covert, Michigan, and it now has the second half of its construction permit application on file [6, 2]. On November 10, 2026, the Nuclear Regulatory Commission published notice (91 FR 72577) that it had received Part 2 of the phased construction permit application from SMR, LLC, on behalf of Palisades SMR, LLC, for a dual-unit SMR-300 plant at the Palisades Energy Center, Docket Nos. 50-616 and 50-617 [1]. The filing, dated September 30, was made under section 103 of the Atomic Energy Act and 10 CFR part 50, and the notice is the first of four weekly notices required by 10 CFR 50.43(a)(3) [1].

What the record shows

What Holtec filed on September 30

Holtec’s transmittal letter, signed by Chairman and CEO Krishna P. Singh, lists five enclosures [2]:

Enclosure Content
I Preliminary safety analysis report (proprietary)
II Preliminary safety analysis report, redacted, non-proprietary
III Updated Quality Assurance Topical Report
IV Exemption requests
V Affidavit under 10 CFR 2.390 to withhold proprietary information

The letter says the safety analysis report follows Regulatory Guide 1.206 “where applicable” and asks the NRC to “docket and review this Construction Permit Application” [2]. The NRC notice describes Part 2 as “a complete preliminary safety analysis report,” a revised version of a quality assurance topical report the NRC had approved earlier, and “a set of exemption requests which address aspects of the CPA that require exemption from the existing rules” [1]. Neither document lists the individual exemptions. The Part 2 package is in ADAMS under Accession No. ML26273A416 [1].

Some Part 1 material is carried forward. The environmental report, the site redress plan and “a proposed license condition related to funding sources” are unchanged, Holtec wrote, and the general and financial information filed with the limited work authorization request is incorporated by reference [2]. That information “is currently under NRC review,” the letter says [2].

The phased route under 10 CFR 2.101(a)(9)

The NRC regulation lets a construction permit applicant that wants to do limited work authorization activities file in two parts. Part one carries the applicant’s general information under section 50.33 and the limited work authorization material required by section 50.10(d); part two carries everything else and “must be submitted no later than 18 months after submission of part one” [7]. Holtec filed Part 1 on December 31, 2025 [4]. Part 2 came nine months later, by this report’s count. In January the American Nuclear Society reported that Holtec’s application documents put Part 2 no later than mid-2027 [11].

What each part would authorize differs. A limited work authorization under 10 CFR 50.10(d) would allow soil improvement within the excavation and installation of certain foundations; a construction permit would authorize full construction of both units [5]. An operating license would be a separate, later application [5, 10].

Where it sits in the process

What has the NRC already decided on Pioneer?

Three steps are complete. NRC staff found Part 1 acceptable for docketing by letter of February 13, 2026, and assigned the two docket numbers [3]. The February 27 notice (91 FR 9892) set a mandatory hearing at a time to be fixed later, opened comment, and gave petitioners until April 28, 2026, to request a contested hearing [4]. Any such hearing was limited to “matters related to 10 CFR 50.33(a) through (f), and the issues under review for Part 1” [4].

On June 15 the NRC announced a single environmental impact statement covering construction, operation and decommissioning, with the U.S. Army Corps of Engineers as a cooperating agency (91 FR 36015) [5]. Then, on August 28, staff issued an exemption from 10 CFR 50.10(c) allowing Holtec to install and leave in place support-of-excavation walls, including diaphragm walls, soldier pile soil-mix walls and perimeter cutoff walls, before any limited work authorization [6]. The exemption states that it “would not constitute a commitment by the NRC to issue an LWA or CP,” and that Holtec assumes the risk of denial [6].

What comes next for Part 2?

The acceptance review is first. If staff accept Part 2 for docketing, the NRC says subsequent notices “will be issued that address the acceptability” of the application and “provisions for participation of the public in the permitting process” [1]. The weekly receipt notices run for four consecutive weeks from November 10 [1].

The February acceptance letter set these estimates for the limited work authorization review [3]:

Milestone Estimated completion
Draft safety evaluation report August 2026
Draft environmental impact statement October 2026
Advanced safety evaluation (no open items) January 2027
Final safety evaluation and final EIS March 2027
Mandatory hearing complete; possible LWA decision by June 2027

The letter excludes contested hearings from that schedule and ties it to NRC issuance of final evaluations on two licensing topical reports by December 2026 [3].

A bill could change the hearing step. H.R. 5549, which the House passed November 11, would amend section 189 a. of the Atomic Energy Act so the NRC may issue a construction permit without a hearing when no affected person requests one, on 30 days’ notice, and it applies “to all applications and proceedings pending before the Nuclear Regulatory Commission” on or after enactment [8]. This site’s November 13 report compares it with the nuclear title of the Senate substitute to H.R. 2347. Under a unanimous consent agreement reached November 12, the Senate is to vote on cloture on that substitute, SA 6883, on Monday, November 16, if the nomination of Daniel Desmond Domenico is confirmed first [9].

What the record does not show

  • Whether the February dates held. No draft environmental impact statement for Pioneer appears in the Federal Register record cited here, though the February letter targeted October 2026 [3]. World Nuclear News reported on October 2 that the draft safety evaluation for the limited work authorization was expected in December 2026, later than the August date in the NRC letter [10, 3]. The NRC has not published a revised schedule in the documents this report draws on.
  • The Part 2 exemptions. The notice and transmittal letter both say Part 2 includes exemption requests, but neither names the rules involved [1, 2].
  • Funding. Part 1 asked for an exemption tied to identifying funding sources, which the NRC is reviewing on the limited work authorization schedule [3]. Holtec says the proposed funding-source license condition is unchanged [2]. The terms of that condition are not set out in either document. The American Nuclear Society reported a $400 million DOE award to Holtec in December 2025 [11].
  • A construction permit date. The February letter gives a possible decision month for the limited work authorization only, not for a construction permit [3].
  • Subsurface questions. The acceptance letter flagged “the stability of subsurface materials and foundations” as an area likely to need increased focus [3]. Whether the preliminary safety analysis report resolves that is not stated in the notice.
  • Unit size. The NRC’s scoping notice says the two units are expected to produce about 680 megawatts electric net [5]. Trade press has given per-unit figures of 340 MWe and about 300 MWe [11, 10].

Positions on the record

Holtec. The transmittal letter asks that the application be docketed and reviewed, and says any updates to the financial information under review “would apply equally to this application” [2]. World Nuclear News reported that Holtec described the filing as its most significant regulatory step to date for the Pioneer plant, said it would next complete a Class 2 construction estimate and a 4D construction simulation, and expects the reactors online in the early 2030s [10]. In its Part 1 application, Holtec requested approval of the limited work authorization by December 31, 2026, according to the American Nuclear Society [11].

NRC staff. In granting the August exemption, staff weighed the factors in 10 CFR 50.12(b) and found that without it, “a significant time delay and increased construction costs could delay construction of Pioneer Units 1 and 2” [6]. Staff prepared an environmental assessment for the exemption and found no significant effect on the human environment [6]. The February letter estimated 6,300 staff hours and $1.2 million in contractor support to decide the limited work authorization application and its three exemptions [3].

Other parties. The environmental review drew scoping comments through July 15, 2026 [5]. The record cited here contains no filed position from a state agency, tribe or opposing group on Part 2, which has not yet been offered for hearing.

Reading-room questions

Questions readers bring to this record, answered from the documents cited below.

Has the NRC accepted Holtec's construction permit application for Pioneer Units 1 and 2?
Not yet. The November 10 notice says NRC staff are conducting an acceptance review of Part 2, and that further Federal Register notices will follow if it is accepted for docketing [1]. Part 1, the limited work authorization request, was docketed in February 2026 [3, 4].
What is in Part 2 of the Pioneer construction permit application?
A complete preliminary safety analysis report, an updated quality assurance topical report and a set of exemption requests [1, 2]. The environmental report, site redress plan and proposed funding-source license condition filed in Part 1 are unchanged [2].
When could Holtec start building the Pioneer SMRs at Palisades?
Some work is already allowed: an August 28, 2026 exemption lets Holtec build permanent excavation support walls before a limited work authorization [6]. The NRC's February schedule estimated a decision on the limited work authorization could come by June 2027, and full construction needs a construction permit [3, 5].
Can the public request a hearing on the Pioneer construction permit?
The NRC says that if Part 2 is docketed, later notices will set out how the public can participate [1]. The hearing opportunity offered in February was limited to Part 1 issues and 10 CFR 50.33(a) through (f) [4].
Would H.R. 5549 remove the mandatory hearing for Pioneer?
If enacted as passed by the House, it would let the NRC issue a construction permit without a hearing when no affected person requests one, after 30 days' notice, and it applies to applications already pending [8]. The Senate had not acted on it as of the record cited here [9].

Note on sourcing

The Part 2 application has been received but not docketed; the NRC staff's acceptance review was under way as of the November 10 notice, and the contents described here are those listed in Holtec's transmittal letter and the NRC notice, not a review of the preliminary safety analysis report itself, much of which Holtec filed as proprietary. The review dates cited are the estimates in the NRC staff's February 13 acceptance letter for the limited work authorization; the NRC has not published a revised schedule in the record this report draws on, and World Nuclear News reported in October that the draft safety evaluation was then expected in December 2026. This report does not draw on the NRC's adjudicatory docket for Pioneer and does not address whether any hearing petition was filed by the April 28 deadline. Unit ratings differ by source: the NRC's scoping notice gives about 680 MWe net for the two units, the American Nuclear Society reported 340 MWe per unit, and World Nuclear News reported about 300 MWe. The $400 million DOE figure is as the American Nuclear Society reported it. The nine-month interval between Part 1 and Part 2 is this report's count from the filing dates. No statement from groups opposing the project appears in the record this report draws on.

Sources

  1. SMR, LLC; Palisades SMR, LLC; Pioneer Units 1 and 2; Receipt of Construction Permit Application (91 FR 72577, FR Doc. 2026-22884)U.S. Nuclear Regulatory Commission, November 10, 2026 · govinfo.gov
  2. Holtec International, Submittal of the Construction Permit Application for Pioneer Units 1 and 2, Transmittal No. 300-USNRC-26018 (ADAMS ML26273A417)Holtec International, September 30, 2026 · nrc.gov
  3. Acceptance Review Results for a Limited Work Authorization Application for SMR-300 Pioneer Units 1 and 2 (ADAMS ML26041A223)U.S. Nuclear Regulatory Commission, February 13, 2026 · nrc.gov
  4. SMR, LLC; Pioneer Units 1 and 2; Phased Construction Permit Application—Limited Work Authorization: acceptance for docketing and opportunity to request a hearing (91 FR 9892, FR Doc. 2026-03943)U.S. Nuclear Regulatory Commission, February 27, 2026 · govinfo.gov
  5. Palisades SMR, LLC; Pioneer Units 1 and 2; Notice of intent to prepare an environmental impact statement and conduct scoping (91 FR 36015, FR Doc. 2026-11915)U.S. Nuclear Regulatory Commission, June 15, 2026 · govinfo.gov
  6. SMR, LLC; Palisades SMR, LLC; Pioneer Units 1 and 2; Exemption (91 FR 55628, FR Doc. 2026-17626)U.S. Nuclear Regulatory Commission, August 28, 2026 · govinfo.gov
  7. 10 CFR 2.101, Filing of applicationU.S. Nuclear Regulatory Commission, accessed 2026-11-14 · ecfr.gov
  8. H.R. 5549, Efficient Nuclear Licensing Hearings Act (Engrossed in House)U.S. House of Representatives, November 11, 2026 · govinfo.gov
  9. Congressional Record, Daily Digest (November 12, 2026), Senate, pp. D1017-D1019U.S. Senate, November 12, 2026 · govinfo.gov
  10. Second part of construction permit application submitted for SMRs at PalisadesWorld Nuclear News, October 2, 2026 · world-nuclear-news.org
  11. Holtec submits partial construction permit application for SMRs at PalisadesAmerican Nuclear Society, January 14, 2026 · ans.org

Subject headings

Cross-references

Other register entries filed under the same subject headings.

  1. No. 0046 · Guidance · 2 shared headingsNRC issues final guidance DANU-ISG-2026-02 for applicants citing DOE or Department of War reactor authorizations
  2. No. 0032 · Rule · 2 shared headingsNRC sets fixed deadlines for contested licensing hearings in final rule, 91 FR 69446, effective Dec. 3
  3. No. 0038 · Bill · 1 shared headingHouse passes six Atomic Energy Act bills, including H.R. 5549 on uncontested NRC hearings; four match text in Senate substitute SA 6883