Register entry No. 0043Environmental reviewWestern Gateway, HF Sinclair, ONEOK proposals
BLM opens EIS scoping for Phillips 66's Western Gateway fuel pipeline, 91 FR 73793, with comments due Dec. 17
The Arizona State Director's notice of intent covers a right-of-way under Mineral Leasing Act section 28 for 887 miles of new refined products pipe from Borger, Texas, to Buckeye, Arizona. About 170 of those miles cross BLM land; BLM projects a record of decision in May 2028.
- Entered by
- Public Record Service
- Date
- Sources
- 7 cited
Summary
Of the 887 miles of new fuel pipeline Phillips 66 proposes to build between Borger, Texas, and Buckeye, Arizona, about 170 cross land managed by the Bureau of Land Management, and that federal share is what brings the project into a full environmental review [1]. On November 17, 2026, BLM Arizona State Director Raymond Suazo published a notice of intent at 91 FR 73793 (FR Doc. 2026-23368) to prepare an environmental impact statement on whether to grant the project a right-of-way under section 28 of the Mineral Leasing Act, 30 U.S.C. 185 [1]. Scoping comments are due December 17, 2026 [1].
What the record shows
The proposed action
The notice describes two new segments: a 20-inch line from Borger to El Paso, Texas, and a 24-inch line from El Paso to Buckeye, west of Phoenix, carrying “refined liquid petroleum products (i.e., gasoline, diesel, jet fuel)” [1]. Pump stations, mainline valve stations, breakout facilities and access roads would be added along the route [1].
BLM is weighing a single action alternative against no action. Under the proposed action, BLM would issue “a 30-year ROW grant and any necessary temporary use permits” on federal land [1]. Thirty years is the statutory ceiling: section 185(n) limits each grant to a reasonable term “but in no event more than thirty years,” renewable under the same section [3]. Under the no-action alternative BLM would deny the application [1]. The notice invites cooperators, tribes and the public to propose other alternatives during scoping [1].
Where the line runs
The notice breaks out the federal mileage by office [1]:
| Land manager | Approx. miles |
|---|---|
| BLM Las Cruces District Office (N.M.) | 101 |
| BLM Carlsbad Field Office (N.M.) | 31 |
| BLM Roswell Field Office (N.M.) | 16 |
| BLM Safford Field Office (Ariz.) | 9 |
| BLM Lower Sonoran Field Office (Ariz.) | 9 |
| BLM Tucson Field Office (Ariz.) | 4 |
| Department of War, Fort Bliss (Texas) | 16 |
| Bureau of Reclamation, Central Arizona Project Canal | 0.3 |
| Fish and Wildlife Service, Gila River Waterfowl Management Area | 0.25 |
The remainder is about 228 miles of state and county land and 472 miles of private land, so roughly one-fifth of the route is federal, by this report’s arithmetic [1]. The line would also cross the Rio Grande, which falls under the International Boundary and Water Commission [1].
The permanent corridor would “typically be 30 feet wide,” with a 60-foot temporary construction strip on top of that [1]. The Mineral Leasing Act caps a right-of-way at fifty feet plus the ground the pipe and related facilities occupy, unless the agency records a finding that more is needed [3].
Why BLM is the lead agency
Because the pipe would cross land administered by two or more federal agencies, BLM is the designated lead agency, and any grant would issue “with the concurrence of each respective land-managing agency” [1]. Reclamation, Fish and Wildlife and the Department of War may use the EIS for their own decisions [1]. The notice lists the other permits expected, among them a Clean Water Act section 404 permit from the Army Corps of Engineers, Endangered Species Act consultation with Fish and Wildlife, section 401 certifications and air permits from the Texas, New Mexico and Arizona environmental agencies, and an outgrant from the boundary commission [1].
Species named for analysis include the lesser prairie-chicken, Sonoran Desert tortoise, southwestern willow flycatcher, yellow-billed cuckoo, dunes sagebrush lizard and cactus ferruginous pygmy-owl, along with caves and karst, playas and national historic or scenic trails [1]. BLM invited 31 tribal nations to government-to-government consultation in July 2026 and says it will use the NEPA process for Section 106 historic preservation review [1].
The larger system
The federal action covers only the new pipe. The notice says the project would tie into Kinder Morgan’s Santa Fe Pacific Pipeline between Colton, California, and Buckeye, “which would be reversed to enable east-to-west product flows,” and into Phillips 66’s Gold Pipeline from Borger to St. Louis, also to be reversed [1]. Together the pieces would form a 1,300-mile system carrying products “from Illinois refineries to California,” but construction “would occur only along the 887-mile portion” [1].
The companies describe that system somewhat differently. Kinder Morgan’s project page calls the new segment “an approximately 900-mile new-build pipeline from Borger, Texas to Phoenix, Arizona,” with supply from St. Louis and “expanded Gulf Coast origin points” [6]. Phillips 66, Kinder Morgan and HF Sinclair announced a joint venture and final investment decision on August 11, 2026 [6]. Oil & Gas Journal reported ownership of 49.9%, 35.1% and 15.0%, an enterprise value of about $5 billion, initial capacity of 230,000 b/d and support “primarily by 10-year take-or-pay transportation agreements” [5].
Where it sits in the process
What is the Western Gateway pipeline review timeline?
The notice starts a 30-day scoping period [1]. BLM’s November 16 release set two virtual meetings, on December 1 and December 2 [2]. Comments filed after the later of December 17 or 15 days past the last meeting “will not be considered,” the notice says [1].
BLM projects a final EIS in February 2028 and a record of decision in May 2028 [1]. The notice cites 42 U.S.C. 4336a(c) as authority [1]. Under section 4336a(g), a lead agency must finish an EIS within two years of the earliest of three triggers, one of which is the notice of intent [4]. Counting from the November 17, 2026 notice alone, that puts the outer limit at November 2028, by this report’s count; BLM’s own schedule falls inside it.
The companies target completion in 2029, “subject to permitting and regulatory approvals” [5].
The 24-inch segment and Congress
Section 185(w)(2) requires the Secretary to notify the House Natural Resources and Senate Energy and Natural Resources committees on receipt of a right-of-way application “for a pipeline twenty-four inches or more in diameter” [3]. No such grant may issue until a notice of intention to grant, with the agency’s detailed findings on terms and conditions, has gone to those committees [3]. The El Paso-to-Buckeye segment is 24 inches [1].
What the record does not show
- Committee notice. The notice of intent does not say whether Interior has sent the section 185(w)(2) notice of the application to the two committees [1, 3].
- An acreage figure that adds up. The notice lists corridor impacts of 2,033 acres of federal land, 2,496 acres of state and county land and 5,149 acres of private or unknown land, “for a total of 9,768 acres” [1]. The three figures add to 9,678 acres, by this report’s arithmetic. Facility workspaces outside the corridor add about 5,523 acres more [1].
- Pipe size on federal land. The proposed action describes “a 20-inch, or 24-inch diameter” pipeline on federal land without assigning mileage to each size on BLM parcels [1].
- Route alternatives. Only the proposed action and no action are on the table, and any width beyond the statutory fifty feet would need a recorded finding that the notice does not yet contain [1, 3].
- The Plan of Development. The notice says further permitting details are in the Plan of Development, which “will be available” on the project page; the notice itself does not reproduce them [1].
- Market questions. Throughput, tariffs and which shippers signed the 10-year contracts are outside BLM’s notice [1, 5].
Positions on the record
BLM. The bureau’s release says the pipeline would deliver gasoline and diesel from the Mid-Continent and Gulf Coast “supporting a more reliable fuel supply for local communities,” and ties the project to Executive Order 14154 and Secretary’s Order 3418 [2]. It calls the start of the analysis “an important step in strengthening the nation’s energy reliability and resiliency” [2].
The sponsors. Kinder Morgan Chief Executive Kim Dang said in August that the project “brings together strategic supply access, existing infrastructure and experienced operators to improve affordability and assurance of supply for customers in the Western United States” [5].
Skeptics. Before the investment decision, Reuters reported that Phillips 66’s Los Angeles refinery began winding down in September 2025 and Valero’s Benicia refinery planned to close, together leaving a supply gap of nearly 280,000 b/d that three competing pipeline proposals aimed to fill [7]. Marathon Petroleum Chief Commercial Officer Rick Hessling told Reuters that “In terms of the pipelines that are rumored to come into the region, I would say that’s a big if” [7]. Valero Chief Operating Officer Gary Simmons said, “We like the waterborne option because it allows you to source barrels from anywhere in the world and take advantage of international arbs that can be open” [7]. Skip York of Turner, Mason & Co. said, “When you see multiple pipeline projects being proposed at the same time, typically only one of them gets done” [7].
Others. Statements from conservation groups, tribes, counties or the three state environmental agencies do not appear in the record this report draws on. The window for them to enter it closes December 17 [1].
Reading-room questions
Questions readers bring to this record, answered from the documents cited below.
- When are comments due on the Western Gateway pipeline EIS?
- BLM asks for scoping comments by December 17, 2026, or 15 days after the last public scoping meeting, whichever is later [1]. Comments can be filed through the project's National NEPA Register page or mailed to the BLM Arizona State Office in Phoenix [1, 2].
- When are the Western Gateway public scoping meetings?
- BLM's release lists two virtual meetings: December 1 from 9 to 10 a.m. and December 2 from 6 to 7 p.m., Mountain Standard Time [2]. The notice allows for up to three meetings on Zoom, with dates announced by postcard, letter and on the project page [1].
- When will BLM decide on the Western Gateway right-of-way?
- BLM's notice projects a final EIS in February 2028 and a record of decision in May 2028 [1]. The Arizona State Director is the deciding official [1].
- How much of the Western Gateway route is on federal land?
- About 170 miles cross BLM-administered land in New Mexico and Arizona, plus about 16 miles of Fort Bliss and short crossings of Bureau of Reclamation and Fish and Wildlife Service land [1]. The rest of the 887 miles is about 228 miles of state and county land and 472 miles of private land [1].
- Does the BLM review cover reversing the Kinder Morgan and Gold pipelines?
- No construction on those lines is within the proposed action. The notice says construction would occur only on the 887-mile Borger-to-Buckeye portion, while the existing Santa Fe Pacific and Gold pipelines would be reversed [1].
Note on sourcing
The application, the Plan of Development and the list of permits come from BLM's notice and its November 16 release; Phillips 66's February 11, 2026 right-of-way application itself is not quoted here. Ownership shares, capacity, cost and the 10-year contracts are the companies' figures as reported by Oil & Gas Journal and Kinder Morgan, and the companies describe the new pipe as about 900 miles ending at Phoenix while BLM's notice gives 887 miles ending at Buckeye; the piece uses BLM's figures for the federal action. The acreage sum, the share of the route on federal land and the latest NEPA completion date under 42 U.S.C. 4336a(g) are this report's own arithmetic from the notice and the statute. The views of refining executives date from November 2025, before the companies' August 2026 investment decision. No scoping comments, cooperating agency agreements or tribal positions were public as of publication.
Sources
- Notice of Intent To Prepare an Environmental Impact Statement for the Proposed Western Gateway Pipeline Project (91 FR 73793, FR Doc. 2026-23368)Bureau of Land Management, November 17, 2026 ·
govinfo.gov - BLM Initiates Environmental Review of Proposed Western Gateway Fuel PipelineBureau of Land Management, November 16, 2026 ·
blm.gov - 30 U.S. Code § 185, Rights-of-way for pipelines through Federal landsU.S. Congress, accessed 2026-11-18 ·
law.cornell.edu - 42 U.S. Code § 4336a, Preparation of environmental documentsU.S. Congress, accessed 2026-11-18 ·
law.cornell.edu - Phillips 66, Kinder Morgan, HF Sinclair sanction Western Gateway pipelineOil & Gas Journal, August 12, 2026 ·
ogj.com - Western Gateway Pipeline Project (project overview)Kinder Morgan, accessed 2026-11-18 ·
kindermorgan.com - California Refinery Closures Spark Pipeline Race to West Coast (Reuters, by Shariq Khan and Nicole Jao)Reuters (via Insurance Journal), November 21, 2025 ·
amp.insurancejournal.com
Subject headings
Cross-references
Other register entries filed under the same subject headings.
- No. 0025 · Environmental review · 2 shared headingsBLM opens supplemental EIS on Seminoe Pumped Storage Project, moving FERC license order to October 2027, P-14787-004
- No. 0022 · Report · 2 shared headingsBLM proposes 60-day permitting track for NPR-A oil production sites, RIN 1004-AF57, 91 FR 57091
- No. 0020 · Record of decision · 2 shared headingsOSM approves Navajo Mine No Name coal permit application in combined final EIS and record of decision, 91 FR 56204